Scheduling semi finished in CRP

$
0
0

Dear Expert,

 

I have Finished product A  is made of semi finished product B and C

 

I have this scenario : for order for semi finished product C , order start date 01.07.13 ,after dispatch becomes  02.07.13 ,  this scheduling will affect the start date of the next level of semi finished B as planned 02.07.13 , now this order for product B should start 03.07.13 based on availability of product C . I found this order for product B start also in the same date 02.07.13 .

 

How I can Rescheduling all levels in CRP , as I have huge number of data and orders and I need easy way to achieve this ?

 

Regards

 

Rami