Dear Expert,
I have Finished product A is made of semi finished product B and C
I have this scenario : for order for semi finished product C , order start date 01.07.13 ,after dispatch becomes 02.07.13 , this scheduling will affect the start date of the next level of semi finished B as planned 02.07.13 , now this order for product B should start 03.07.13 based on availability of product C . I found this order for product B start also in the same date 02.07.13 .
How I can Rescheduling all levels in CRP , as I have huge number of data and orders and I need easy way to achieve this ?
Regards
Rami