Hello everybody,
I'm need to create a new factory calendar and I found some steps to how to do it, but unfortunately, I didn't found any document explaining how the Factory Calendar works and the impacts, and I have some doubt about the risks that could appears, like:
1 - Is there any risk or impact if I create a new Factory Calendar and attached it in new projects? Thinking in others modules in SAP, I need to configure others environment that wasn't the transaction SCAL, CJ20N or OPSA?
2 - If I modify any Factory Calendar that was in production and attached in some projects that didn't finished yet, what risks could be happen?
3 - Is it possible to create a range of 'holydays' as a floating public holyday? I mean, during 2 weeks in the year (Christmas and New Year's Weeks) some projects didn't work, I'm trying to configure and noticed that I need to inform every day and month in the range by year.
I really appreciate if anyone could help me or have any documentation about this.
Thank You!
Best Regards,
Raphael Palmieri