Hi guys,
We have two plants one in Maxico and another in china
i have selected same process order type to create process orders in both plants.
when i am saving the process order system is printing the process order but for Maxico plant i am getting the bar-code of materials which are assigned to phases or operation but for china plant i am not getting bar-code of materials. i am getting the bar-code of operation start and end for both the plants but not for material.
In T-code CB85 i have checked the configuration for both plants and order type same form is there same print program is there. but why system is printing the bar-code for maxico plant but not for china plant.
Please help.
Regards,
Dheeraj Rawal