Hi PP experts,
I am facing the issue planned order dates are showing in past date due to SubReq date showing in past.
2000425 is head material for 2000426.
but I have checked all back materials requirement means header material requirement in MD04, there is not showing the requirement in past.
Kindly help.
Regards,
Santosh Sharma