Hello,
I am having a problem in sap bpm process.
I created a simple process input name and age and output them.
When i deployed and run it i have 2 ui's input ui and output ui.
When i input some data and approved it. The process ui is removed from the universal worklist.
But in the process diagram the green token still stays for a while (more than 30 sec) even after i approved the process.
The universal list was empty. After a while the output ui appears.
I do not have any pi integrations or BRM rules. Just input and out put.
I neve had this kind of delay before.
I do not know what happend in the backend of the server.
Can anybody give me some idea that i can solve this performance probelem for my project. This is a simple example takes so long, i can not imagin how long the real project will take.
Any suggestions are appreciated.
Thanks in advance
Regards,
Antony