Hi,
I am trying to send forward dependant demand from one system to another system via LOISTD01 idoc. Hpw do I account for any change in dependant demand in the source system ? For eg today I send forward a depdenedant rew of 10 ea to the target system for which the target system creates a planned order. Tomorrow if the dependant requirement in the source system increases to 15 ea then how can I delete the dep req of 10 ea which I sent today and repalce that with the new 15 ea so that the source system creates a planned order for the balance of 5 ea and not a new planned order of 15 ea in addtion to the original planned order of 10 ea ?
Thanks